Every utilities company facing critical shortages for repairs and maintenance
Still an issue, I work for a utility and lead times for things like high voltage transformers are still ~18 months or so from what I’ve been told
Coincidentally, I also processed a shipment of smaller transformers that came thru from South Korea (which for us was unheard of)
It’s not ideal
so what youre telling me is that if a group of organized people wanted, they could take out the entire us electrical grid by blowing up a bunch of transformers?
HUH
Attack on Nine Substations Could Take Down U.S. Grid (2014)
https://spectrum.ieee.org/attack-on-nine-substations-could-take-down-us-grid